Landfill facilities

Closure and reclamation of the landfill for municipal solid waste

Closure and reclamation of the landfill for municipal solid waste in the Municipality of Oryahovo - 2014

Closure and reclamation of the landfill for municipal solid waste in the Municipality of Oryahovo - 2014

 



Completed are the types of work by parts:

 

  • excavation and removal of waste - 39 912 cub. m;

  • leveling the layer of earth 20 cm - 1660 cub. m;

  • clay screen 50 cm thick - 4150 cub. m;

  • blanket drainage 50 cm thick - 4150 cub. m;

  • sub humus layer with a thickness of 30 cm - 2490 cub. m;

  • soil-building humus layer with a thickness of 20 cm - 1660 cub. m;

  • drainage pipes - 704 m;

  • embankment ditch - 620 m;

  • lined ditch - 50 m;

  • monitoring wells - 3 pcs .;
    • depth level benchmark - 1 pc .;
    • leveling benchmarks for subsidence the landfill - 2.

     

In biological reclamation 1-st year were performed the following works:

  • fertilization and planting saplings - 11852 pcs.;

  • fertilizing and seeding with grass mixtures – 3.675 acres.

Related projects

Extension, upgrade and renovation of the hotel "Serdika", village of Kranevo
Hotel and holiday buildings

Extension, upgrade and renovation of the hotel "Serdika", village of Kranevo

Extension, upgrade and repair of hotel “Serdika“ and in RLP in the village of Kranevo, Balchik Municipality - 2012

Warehouse
Industrial and infrastructure projects

Warehouse

Warehouse, located in RLP II-196 T-T2 on the plan of village Topoli, municipality of Varna - 2012